Build the schedule from the dispatch deadline
Use columns for task, predecessor, duration, latest finish, owner and evidence. Starting at live dispatch, work backwards through trial dispatch, commissioning, installation and handover. If commissioning takes five days and trial dispatch takes two, installation must finish at least seven working days before the live date, before any contingency.
Related reading Warehouse Fit-Out Costs: What to Budget Beyond Rent.
If you’re shortlisting local properties, use this guide when evaluating Mansi Industrial Park.

Leave a Reply