Warehouse Fit-Out Timeline Template

Build the schedule from the dispatch deadline

Use columns for task, predecessor, duration, latest finish, owner and evidence. Starting at live dispatch, work backwards through trial dispatch, commissioning, installation and handover. If commissioning takes five days and trial dispatch takes two, installation must finish at least seven working days before the live date, before any contingency.