Use handover to check whether the space matches the agreed specification and is ready for fit-out. Bring the signed scope and a marked-up plan so each issue can be tied to a location.
Inspect the building with the landlord
Walk the roof drainage points, floor joints, dock doors and yard. Have the relevant specialists check utilities and review the records for systems that must be commissioned. Photograph defects and record meter readings.
Create a dated list of outstanding items with an owner and completion date. Record which items prevent occupation and align the handover record with the agreed rent commencement terms.
For base-rent benchmarks and worked examples, see Warehouse Rent in Sriperumbudur and Oragadam.
Related reading
Grade A Warehouse Specifications Checklist
Warehouse Relocation Planning: How to Avoid Dispatch Delays
Inspect yard drainage after rain and document possession
Photograph ponding, drains, roof outlets, dock thresholds and the approach after rain when conditions allow. Before taking possession, record meter readings, keys and defects on a marked plan. Have both parties acknowledge the dated condition record.